2010年8月,在昌原的Hyosung工廠,機艙的工廠測試以及IO測試成功完成。僅僅在3周之后,Hyosung就在Jeju島上完成了新2MW樣機的安裝以及主線纜的最后安裝。
調試以及并網
Kk人員親自前往風場參與調試工作。第一階段首先確認所有的安全設備以及控制系統都工作正常。最后一周,即調試完成僅2周之后,就完成風機與電網并網發電。
里程碑
在如此短的時間內就能并網發電確實是不小的成就。Kk以及Hyo-sung在此項目上的專注,過硬的技術,良好的合作以及很好的適應能力是此項目成功的關鍵。雙方都對此成就感到驕傲。在接下來的時間,風機會全功率運行,風機的認證準備工作也將開始。
The Hyosung - 2 MW project successfully up and running within scheduled time
August 2010 the Factory Acceptance Test, FAT (I/O test) of the nacelle was completed with success at Hyo-sung’s factory in Changwon. Only 3 weeks later Hyosung was able to finish the erection of the new 2MW protoype turbine on Jeju Island, as well as final installation of the main cables.
Commissioning and on grid
kk-electronic went on-site to participate in the commissioning of the turbine. The first period of time was spent on confirming that all safety and control systems were working correctly. Last week, after only two weeks of commissioning, the turbine was connected to the grid and producing power.
Reaching the milestone
Reaching the milestone of producing power to the grid within this short period of time is quite an achievement. Focus, proper craftsmanship, good cooperation and flexibility from both Hyo-sung and kk made this achievement possible. Both Hyosung and kk can be very proud of this achievement. In the coming days the power production will be increased to full capacity and preparations for certification of the turbine will begin.
Hyosung 集團副總裁Dong-Soon(Dan) Kim先生表示:“我們對kk電子為按時完成測試以及調試工作所投入的熱情及努力非常滿意”。
“We are very satisfied with the effort and enthusiasm shown by kk-electronic in order to complete the tests and commissioning in time” Mr. Dong-Soon(Dan) Kim, Vice President Hyosung Corporation