當(dāng)前位置: 東方風(fēng)力發(fā)電網(wǎng)>談技術(shù) >基礎(chǔ)知識(shí) > 雙饋異步發(fā)電機(jī)與同步發(fā)電機(jī)的比較

雙饋異步發(fā)電機(jī)與同步發(fā)電機(jī)的比較

2010-09-09 來源:互聯(lián)網(wǎng)轉(zhuǎn)載 瀏覽數(shù):2352

In picture 1 we can see the circuit of the system using a synchronues generator, a diode rectifier, a dc-link step-up-chopper and an IGBT converter.
在圖1中,我們可以看到該系統(tǒng)的電路:同步發(fā)電機(jī),二極管整流橋,連接在直流母線上的升壓器,一個(gè)IGBT變流器。

In picture 2 we can see an asynchronues generator with slip rings, an IGBT rectifier, a dc-link, and an IGBT converter. This system is used by some other companies.
在圖2中,我們可以看到:一個(gè)帶滑環(huán)的異步發(fā)電機(jī),IGBT整流橋,直流母線,IGBT變流器。有一些公司使用該系統(tǒng)。

In Germany the first big wind turbine with variable speed had been developed in 1980 (3mW, 100m rotor diameter), but the project was to big an was not successful because of mechanical problems. At this time the cost for power semiconductors was very high, so the turbine used a double feed asynchronues generator with a small slip to save converter cost.
在德國,第一臺(tái)大型的變速風(fēng)力發(fā)電(3兆瓦,轉(zhuǎn)子直徑達(dá)10米)設(shè)備誕生于1980年,但是由于機(jī)械問題,該項(xiàng)目并不是很成功。那時(shí)候,電力器件的成本相當(dāng)?shù)母撸虼耍L(fēng)力發(fā)電設(shè)備就經(jīng)常采用帶小滑差的雙饋異步發(fā)電機(jī)來節(jié)省變流器的成本。
Commercial wind turbines with variable speed with 750kW and more had been developed in Denmark and Germany since 1995.
真正用于商業(yè)運(yùn)行的750kw變速甚至更大的風(fēng)力發(fā)電設(shè)備在1995年誕生于丹麥和德國。
The Danish manufacturers had been starting with constant speed turbines. This is mainly because the wind in Denmark is more constant compared to Germany. But for turbines above 1 MW they also started to take variable speed because of problems they had with the gearboxes. But first the Danish manufacturers also used a small slip and therefore a double feed system seemed more economical.
丹尼斯設(shè)備廠開始時(shí)設(shè)計(jì)恒速風(fēng)電設(shè)備。這主要是由于跟德國相比,丹麥的風(fēng)速比較穩(wěn)定。但是對(duì)于1兆瓦以上的風(fēng)電設(shè)備,由于齒輪箱設(shè)計(jì)的問題,他們也開始采用變速方案。但是剛開始時(shí),丹尼斯設(shè)備廠仍采用小滑差,所以雙饋系統(tǒng)也就比較經(jīng)濟(jì)。
In 1988 the first 50kW turbine using a synchronues generator and an 6 pulse thyristor converter. Later used 12pulse converters, but this technique could not be used further on because of harmonic distortion.
1988年,第一臺(tái)50千瓦的風(fēng)力發(fā)電設(shè)備是采用同步發(fā)電機(jī)和六脈沖可控硅變流器。后來,采用12脈沖變流器,但是由于諧波失真的緣故,后來這種技術(shù)就沒有再持續(xù)。

Started in 1993 with a 750kW double feed system. Many problems with the slip rings. The generator which was produced by a big Austrian company had to be changed 5 times and still did not run more than two months. After one year they gave up the double feed system and changed it to an synchronues generator. We found that the cost of the converter was not more than the double feed system because the construction is more simple.
開始于1993年的750千瓦雙饋異步系統(tǒng),其中的滑差環(huán)一直存在問題,由澳大利亞一家大公司生產(chǎn)的發(fā)電機(jī)也修改了5次,但是運(yùn)行時(shí)間仍舊不到兩個(gè)月。一年以后,他們放棄了雙饋異步系統(tǒng),并把異步發(fā)電機(jī)換成同步發(fā)電機(jī)。我們發(fā)現(xiàn),由于同步系統(tǒng)的結(jié)構(gòu)變得更加簡單,因此同步系統(tǒng)變流器的成本并沒有比雙饋異步系統(tǒng)的高。

【延伸閱讀】

標(biāo)簽:

閱讀上文 >> 西北電網(wǎng)風(fēng)力發(fā)電功率補(bǔ)償問題探討
閱讀下文 >> 風(fēng)力發(fā)電機(jī)風(fēng)輪現(xiàn)存在的問題和改進(jìn)方向

版權(quán)與免責(zé)聲明:
凡注明稿件來源的內(nèi)容均為轉(zhuǎn)載稿或由企業(yè)用戶注冊(cè)發(fā)布,本網(wǎng)轉(zhuǎn)載出于傳遞更多信息的目的,如轉(zhuǎn)載稿涉及版權(quán)問題,請(qǐng)作者聯(lián)系我們,同時(shí)對(duì)于用戶評(píng)論等信息,本網(wǎng)并不意味著贊同其觀點(diǎn)或證實(shí)其內(nèi)容的真實(shí)性;


本文地址:http://www.jiechangshiye.com/tech/show.php?itemid=7240&page=1

轉(zhuǎn)載本站原創(chuàng)文章請(qǐng)注明來源:東方風(fēng)力發(fā)電網(wǎng)

按分類瀏覽

點(diǎn)擊排行

圖文推薦

推薦談技術(shù)

主站蜘蛛池模板: 扎赉特旗| 开原市| 张家口市| 湄潭县| 砚山县| 西安市| 湟中县| 东乡县| 通辽市| 博客| 龙门县| 眉山市| 星子县| 含山县| 台南市| 永定县| 阳泉市| 刚察县| 鸡西市| 延吉市| 惠州市| 郓城县| 门源| 龙里县| 南充市| 石台县| 广汉市| 剑阁县| 郸城县| 特克斯县| 临洮县| 信丰县| 昭通市| 通州区| 平邑县| 绥德县| 开鲁县| 宽城| 玉龙| 永靖县| 康定县|